Hot work permits: what they must include and how to issue one

A hot work permit is a written permit-to-work that authorises welding, cutting, grinding, brazing, torch-on roofing or any other work producing heat or sparks, at a set place and time. It lists the fire hazards, the precautions that must be in place before work starts, who authorised it, and a fire watch that continues after the work ends, commonly for at least 60 minutes. A permit normally lasts no longer than one shift.

Written by Thomas Featherstone TechIOSH, NEBOSH IGC-qualified and IOSH Managing Safely trained · Reviewed October 2026

What counts as hot work?

Hot work is any work that uses or produces a flame, sparks or enough heat to ignite materials nearby. Common examples:

Hot work is a major cause of fires in buildings under construction or refurbishment, and fires often start hours after the work has finished, from sparks smouldering in dust, insulation or a cavity.

Do you legally need a hot work permit?

No UK regulation names a “hot work permit” as a general requirement, but several duties together mean you need a formal system of control, and a permit is the recognised way to provide one:

What a hot work permit must include

Use this as the structure for your own permit form. Every section should be completed before the work starts, except the fire watch and handback, which are completed afterwards.

SectionWhat it records
Permit number and validityA unique reference, the date, and the start and finish time. A hot work permit normally covers one task for no longer than one shift.
Location and descriptionExactly where the work will happen (building, floor, room, roof area) and what is being done, with what equipment.
PeopleThe authorising person, the person in charge of the work (permit holder), the operatives and the fire watcher, each named.
Hazards identifiedCombustible materials, flammable liquids, gases or dust, hidden voids and cavities, insulation, services, and areas on the other side of walls, floors and ceilings.
Precautions checklistEach precaution ticked as done before work starts (see the checklist below).
Fire detection and alarmsWhether any detectors are isolated, which zone, who isolated them and confirmation they are reinstated afterwards.
Emergency arrangementsHow to raise the alarm, extinguishers at the point of work, the escape route and the site's emergency contact.
Authorisation and acceptanceSignatures from the authorising person and the permit holder confirming the precautions are in place and understood.
Fire watch and handbackTimes the work stopped and the fire watch ended, the final check result, and signatures closing the permit.

Hot work precautions checklist

Confirm each of these on site before the permit is signed:

Distances, fire watch periods and extinguisher types vary between insurers and sites. Where your insurer or principal contractor sets a stricter standard, the stricter one applies.

How to issue a hot work permit, step by step

StepWhat to do
1. Ask whether hot work can be avoidedUse cold-cutting, bolted or push-fit joints, or move the item to a workshop. The safest hot work permit is the one you never need to issue.
2. Plan and risk assessIdentify the fire hazards for this job and this location, and decide the precautions. Hot work should be covered by your fire risk assessment.
3. Raise the permitComplete the location, task, people, hazards and precautions sections before anyone starts.
4. Inspect the areaThe authorising person visits the work area, checks every precaution is in place and only then signs.
5. Brief the teamThe permit holder signs to accept the permit, and the operatives and fire watcher are briefed on the precautions and emergency arrangements.
6. Carry out the workKeep the permit at the place of work. Stop work if conditions change or a precaution is no longer in place.
7. Fire watchKeep a fire watch during the work and for the agreed period after it ends, commonly at least 60 minutes, with a further check later.
8. Close the permitReinstate any isolated detection, record the fire watch and final check, sign off and keep the permit with your records.

Who does what

Common hot work permit failures

Hot work FAQs

Common questions

What is a hot work permit?

A hot work permit is a written permit-to-work that authorises a specific piece of hot work, such as welding, cutting or grinding, at a set place and time. It records the fire hazards, the precautions that must be in place before work starts, who authorised it and the fire watch afterwards.

Is a hot work permit a legal requirement in the UK?

No regulation uses the words 'hot work permit' as a general requirement, but employers and those in control of premises must assess and control fire risks under the Regulatory Reform (Fire Safety) Order 2005, provide safe systems of work under the Health and Safety at Work etc. Act 1974, and prevent fire on construction sites under CDM 2015. A permit is the recognised way to meet those duties for hot work, and many insurers make one a condition of cover.

How long is a hot work permit valid for?

Normally for one task in one location for no longer than one shift or working day. If the work continues the next day, or moves to a different area, issue a new permit after a fresh inspection.

How long should a fire watch last after hot work?

Commonly at least 60 minutes after the hot work finishes, with a further check of the area later. Your insurer, the site's fire risk assessment or the Joint Code of Practice for construction sites may require longer, so check which applies.

Who can issue a hot work permit?

A competent authorising person appointed by the organisation in control of the premises or site, who understands the fire risks and has the authority to stop work. They should not normally be the person carrying out the hot work.

Does grinding count as hot work?

Yes. Angle grinding and disc cutting throw hot sparks that can travel several metres and smoulder unseen in debris or gaps, so they should be treated as hot work and controlled with a permit.

Official sources

This is a plain-English summary for UK businesses, not legal advice. Always follow your fire risk assessment, your insurer’s conditions and current guidance on hse.gov.uk.

No more lost paper permits

Issue and close hot work permits with a full audit trail

Featherstone Safety Hub lets you raise, authorise, activate and close hot work, confined space and working at height permits from any device, record the precautions confirmed, and keep a timestamped record of who issued and authorised each one. 14-day free trial, no card required to look around.

Related guides

Free download: a printable RIDDOR decision flowchart with the reporting deadlines, to keep with your accident book. Get the flowchart →

All health & safety guides →