UK compliance guide
Hot work permits: what they must include and how to issue one
A hot work permit is a written permit-to-work that authorises welding, cutting, grinding, brazing, torch-on roofing or any other work producing heat or sparks, at a set place and time. It lists the fire hazards, the precautions that must be in place before work starts, who authorised it, and a fire watch that continues after the work ends, commonly for at least 60 minutes. A permit normally lasts no longer than one shift.
Written by Thomas Featherstone TechIOSH, NEBOSH IGC-qualified and IOSH Managing Safely trained · Reviewed October 2026
What counts as hot work?
Hot work is any work that uses or produces a flame, sparks or enough heat to ignite materials nearby. Common examples:
- Welding and flame cutting
- Grinding and disc cutting that throws sparks
- Brazing and soldering
- Torch-on roofing and other work with a gas torch or blowlamp
- Hot air guns and paint stripping with heat
- Thermal lancing and other heat-producing processes
Hot work is a major cause of fires in buildings under construction or refurbishment, and fires often start hours after the work has finished, from sparks smouldering in dust, insulation or a cavity.
Do you legally need a hot work permit?
No UK regulation names a “hot work permit” as a general requirement, but several duties together mean you need a formal system of control, and a permit is the recognised way to provide one:
- Regulatory Reform (Fire Safety) Order 2005: the responsible person must assess fire risks and put fire precautions in place, which includes controlling ignition sources such as hot work.
- Health and Safety at Work etc. Act 1974: employers must provide safe systems of work.
- CDM 2015: on construction sites, suitable and sufficient steps must be taken to prevent the risk of injury from fire.
- DSEAR 2002: where flammable substances or explosive atmospheres may be present, ignition sources must be controlled.
- Insurance: many property and contractors’ insurers make a hot work permit system a condition of cover. Check your policy wording, because a claim can be refused if the condition was not met.
What a hot work permit must include
Use this as the structure for your own permit form. Every section should be completed before the work starts, except the fire watch and handback, which are completed afterwards.
| Section | What it records |
|---|---|
| Permit number and validity | A unique reference, the date, and the start and finish time. A hot work permit normally covers one task for no longer than one shift. |
| Location and description | Exactly where the work will happen (building, floor, room, roof area) and what is being done, with what equipment. |
| People | The authorising person, the person in charge of the work (permit holder), the operatives and the fire watcher, each named. |
| Hazards identified | Combustible materials, flammable liquids, gases or dust, hidden voids and cavities, insulation, services, and areas on the other side of walls, floors and ceilings. |
| Precautions checklist | Each precaution ticked as done before work starts (see the checklist below). |
| Fire detection and alarms | Whether any detectors are isolated, which zone, who isolated them and confirmation they are reinstated afterwards. |
| Emergency arrangements | How to raise the alarm, extinguishers at the point of work, the escape route and the site's emergency contact. |
| Authorisation and acceptance | Signatures from the authorising person and the permit holder confirming the precautions are in place and understood. |
| Fire watch and handback | Times the work stopped and the fire watch ended, the final check result, and signatures closing the permit. |
Hot work precautions checklist
Confirm each of these on site before the permit is signed:
- Combustible materials removed from around the work, commonly within at least 10 metres, or protected with fire-resistant blankets or screens.
- Floors swept clear of debris; gaps, openings and ducts that sparks could fall through are covered.
- Flammable liquids, gases and aerosols removed from the area.
- Walls, floors and ceilings checked for combustible construction or hidden materials on the other side.
- Suitable fire extinguishers at the point of work, and the operatives trained to use them.
- Gas cylinders secured upright, hoses in good condition, flashback arrestors fitted.
- Any isolation of fire detection limited to the smallest zone necessary, recorded and reinstated.
- A competent fire watcher in place during the work and for the agreed period afterwards.
- Escape routes clear and the means of raising the alarm confirmed.
Distances, fire watch periods and extinguisher types vary between insurers and sites. Where your insurer or principal contractor sets a stricter standard, the stricter one applies.
How to issue a hot work permit, step by step
| Step | What to do |
|---|---|
| 1. Ask whether hot work can be avoided | Use cold-cutting, bolted or push-fit joints, or move the item to a workshop. The safest hot work permit is the one you never need to issue. |
| 2. Plan and risk assess | Identify the fire hazards for this job and this location, and decide the precautions. Hot work should be covered by your fire risk assessment. |
| 3. Raise the permit | Complete the location, task, people, hazards and precautions sections before anyone starts. |
| 4. Inspect the area | The authorising person visits the work area, checks every precaution is in place and only then signs. |
| 5. Brief the team | The permit holder signs to accept the permit, and the operatives and fire watcher are briefed on the precautions and emergency arrangements. |
| 6. Carry out the work | Keep the permit at the place of work. Stop work if conditions change or a precaution is no longer in place. |
| 7. Fire watch | Keep a fire watch during the work and for the agreed period after it ends, commonly at least 60 minutes, with a further check later. |
| 8. Close the permit | Reinstate any isolated detection, record the fire watch and final check, sign off and keep the permit with your records. |
Who does what
- Authorising person: competent, appointed in writing, inspects the area and signs the permit. Should not normally be the person doing the work.
- Permit holder: the person in charge of the hot work, who accepts the permit and makes sure the operatives follow it.
- Fire watcher: stays in the area during the work and for the full watch period afterwards, with an extinguisher and a way to raise the alarm, and does nothing else.
Common hot work permit failures
- Permits signed in the office without anyone visiting the work area.
- One blanket permit covering a whole week, several areas or several contractors.
- Hot work started late in the day, so the fire watch is cut short when the site closes. Plan hot work to finish well before the end of the shift.
- Detectors isolated for the work and never reinstated.
- Sparks travelling through gaps in floors, ducts or cladding into areas nobody checked.
- The fire watcher also doing the hot work, or leaving the area before the watch period ends.
Hot work FAQs
Common questions
What is a hot work permit?
A hot work permit is a written permit-to-work that authorises a specific piece of hot work, such as welding, cutting or grinding, at a set place and time. It records the fire hazards, the precautions that must be in place before work starts, who authorised it and the fire watch afterwards.
Is a hot work permit a legal requirement in the UK?
No regulation uses the words 'hot work permit' as a general requirement, but employers and those in control of premises must assess and control fire risks under the Regulatory Reform (Fire Safety) Order 2005, provide safe systems of work under the Health and Safety at Work etc. Act 1974, and prevent fire on construction sites under CDM 2015. A permit is the recognised way to meet those duties for hot work, and many insurers make one a condition of cover.
How long is a hot work permit valid for?
Normally for one task in one location for no longer than one shift or working day. If the work continues the next day, or moves to a different area, issue a new permit after a fresh inspection.
How long should a fire watch last after hot work?
Commonly at least 60 minutes after the hot work finishes, with a further check of the area later. Your insurer, the site's fire risk assessment or the Joint Code of Practice for construction sites may require longer, so check which applies.
Who can issue a hot work permit?
A competent authorising person appointed by the organisation in control of the premises or site, who understands the fire risks and has the authority to stop work. They should not normally be the person carrying out the hot work.
Does grinding count as hot work?
Yes. Angle grinding and disc cutting throw hot sparks that can travel several metres and smoulder unseen in debris or gaps, so they should be treated as hot work and controlled with a permit.
Official sources
- HSE HSG168 - Fire safety in construction
- HSE - Permit to work systems
- Regulatory Reform (Fire Safety) Order 2005
- Construction (Design and Management) Regulations 2015
This is a plain-English summary for UK businesses, not legal advice. Always follow your fire risk assessment, your insurer’s conditions and current guidance on hse.gov.uk.
No more lost paper permits
Issue and close hot work permits with a full audit trail
Featherstone Safety Hub lets you raise, authorise, activate and close hot work, confined space and working at height permits from any device, record the precautions confirmed, and keep a timestamped record of who issued and authorised each one. 14-day free trial, no card required to look around.
Related guides
More plain-English UK guidance
- Construction phase plans →What a construction phase plan must contain, who writes it and when it is required.
- CDM 2015 explained →Dutyholders, their duties and when CDM 2015 applies to a project.
- How to do a risk assessment →The HSE's five steps, the hierarchy of controls, the types of risk assessment and a worked example.
- RIDDOR reportable incidents →The full list of reportable injuries, diseases and dangerous occurrences, with examples.
- What is RIDDOR? →Who must report, the deadlines that apply and the records you have to keep.
- How long to keep H&S records →Retention periods for accident records, training, assessments and monitoring data.
- Manual handling →The 1992 Regulations, TILE risk assessment, HSE guideline weights and training.
- Near miss and incident reporting →Accident, incident and near miss definitions, what to record and report, and how to investigate.
Free download: a printable RIDDOR decision flowchart with the reporting deadlines, to keep with your accident book. Get the flowchart →